You should always update the proposal before you work with it. Otherwise information about the item that has been changed will not be reflected in the analysis. Note: A proposal that is selected for maintenance or being ordered for update cannot be maintained by someone else until the update is ready or maintenance is ended.
- Select the Work with pull-planning menu item.
- You access Work with pull-planning, Order proposals. Select the analysis proposal you want to update/re-create and click Update proposal.
- You access Analysis proposal creation. Change information in the fields where needed. For example, if you want to work with a re-schedule analysis you need to change the type of proposal to 2. See Create an analysis proposal for pull planning for information about the fields. Click OK to update the analysis proposal. Exit the routine.
Related topics
- About pull planning
- Create an analysis proposal for pull planning
- Set up shortage analysis values for pull planning
- Release manufacturing orders during pull planning
- Release purchase orders during pull planning
- Re-schedule manufacturing orders during pull planning
- Re-schedule purchase orders during pull planning
- Delete an analysis proposal for pull planning