Maintain the operations for an item in a BOM/BOR update proposal

Related topics

  1. Select the Update BOM/BOR from statistics menu item.
  2. You access Work with BOM/BOR update from stat. Select the applicable proposal and click Work w proposal.
  3. You access Work with BOM/BOR update from stat, Item selection. Select the item for which you want to maintain the operations and click Operations.
  4. You access Work with BOM/BOR update from stat, Operations, times in minutes (decimal). Select the operation that you want to change and click Change.
  5. You access Work with BOM/BOR update from stat, Change operation, times in minutes (decimal). (Note: By default the system displays the times in minutes. You can click Minutes/Decimal to view the times in decimals). The original operation times are displayed at the bottom of the panel. The average operation time values suggested for update are displayed in the following fields, but can be changed:
  6. Run and labour time
    Displays the average value calculated from manufacturing history. Leave the suggested value or enter a new run and labour time for the operation.
    Set-up time int
    Displays the average value calculated from manufacturing history. Leave the suggested value or enter a new internal set-up time for the operation.
    Set-up time ext
    Displays the average value calculated from manufacturing history. Leave the suggested value or enter a new external set-up time for the operation.
    Machine time
    Displays the average value calculated from manufacturing history. Leave the suggested value or enter a new machine time for the operation.

    Click OK. Exit the routine.