Operation cost price maintenance, Op Times in Decimal/Minutes (POM060M)

The purpose of this program is to maintain operation hours cost price information. The system will use these cost prices at project/quotation product costing.

Function keys

Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times.
Customer
Project
Status
Displays the status of the project/quotation in the flow.

Valid codes are:

Phase
Line number
Item
Displays the item being maintained.
Variant
Operation number
Work centre
Time basis code

Run and labour time
Displays the run and labour time in hours for the operation, i.e. the actual time spent on the operation. This time is used as a part in the function Project/quotation costing calculation in combination with the operation hours costs.
Set-up time int
Displays the internal set-up time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Set-up time ext
Displays the external set-up time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Machine time
Displays the machine time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Waste percentage
Run and labour price
Enter the hourly price of run and labour time. This is used together with hourly prices for machine time, internal set-up time and external set-up time to calculate the costs of utilising the resources. This price is used as a part in the Project/quotation costing calculation function in combination with the operation times.
Set-up int price
Enter the internal set-up price. This hourly price is used together with hourly prices for machine time, labour time and external set-up time to calculate the costs of utilising the resources. This price is also used as a part in the Project/quotation costing calculation function in combination with the operation times.
Set-up ext price
Enter the external set-up price. This hourly price is used together with hourly prices for machine time, internal set-up time and labour time to calculate the costs of utilising the resources. This price is also used as a part in the Project/quotation costing calculation function in combination with the operation times.
Machine price
Enter the machine price. This hourly price is used together with hourly prices for internal set-up time, labour time and external set-up time to calculate the costs of utilising the resources. This price is also used as a part in the Project/quotation costing calculation function in combination with the operation times.