Note: This panel is only shown if the PCM application is installed and activated. On this panel you enter a project element line that should be linked to the G/L posting.
- PCM project
- Displays the project number that is entered in the project account part of the G/L posting.
- PCM phase
- Enter the project phase to which the G/L posting should be linked.
- PCM WBS code
- Enter the WBS code to which the G/L posting should be linked.
- Document date
- Enter the date that should be allocated to the PCM cost transaction.
- Quantity
- Enter the quantity that should be allocated to the PCM cost transaction.
- Amount
- Displays the amount that is entered on the G/L posting.
- Text
- Enter optional text to be stored for the project transaction.
- Close line
- Indicate if the project WBS code should be closed.