The purpose of this program is to display details of simulation work centre prices. The work centre simulation prices are used in the Product costing function when costing is made for simulation cost.
- Work centre
- Machine price
- This simulation hourly price is used together with times for operations in the Product costing simulation function.
- Run and labour price
- This simulation hourly price is used together with times for operations in the Product costing simulation function.
- Internal set-up price
- This simulation hourly price is used together with times for operations in the Product costing simulation function.
- External set-up price
- This simulation hourly price is used together with times for operations in the Product costing simulation function.
- Overhead 1 %
- This simulation overhead percentage is used together with calculated values for operations in the Product costing simulation function.
- Overhead 2 %
- This simulation overhead percentage is used together with calculated values for operations in the Product costing simulation function.
- Overhead 1 amount
- This simulation overhead amount is used together with calculated values for operations in the Product costing simulation function.
- Overhead 2 amount
- This simulation overhead amount is used together with calculated values for operations in the Product costing simulation function.