The purpose of this program is to get an overview of all included operations times and cost for an item.
Options
Equations | Select this option to view performed equations and values for an operation. |
Function keys
Re-calculate | Re-calculate the product costing. This is mandatory if a new operation has been added or if existing operations have been changed. |
Prev level | Only used if you are viewing lower levels. Return to the previous level. |
- Item
- Calc date
- The date indicates when the right prices and overhead were retrieved.
- Cost model
- The cost model id used for product costing.
- W c price
- The work centre price indicates from where the work centre prices have been retrieved during the product costing calculation.
Code Description 1 Standard 2 Actual 3 Simulation
- Std quant PC
- The quantity in stock unit that the product costing is based on.
- Struct quant
- Variant
- Warehouse
- Struct unit
- Op no
- Operation description
- Work centre
- TB-code
- Line amount
- The calculated cost for an operation presented in system currency for one parent item unit.
- C
- Indicates if the operation has been changed, either via the Change option or by adding a new operation.