The purpose of this program is to view material and capacity clearance for an existing manufacturing order.
- Order number
- Critical resrcs only
- This field is only displayed if the Manufacturing finite planning functionality is activated in Work with companies. Indicates if only critical resources should be taken into consideration when controlling if capacity exists to produce the entered quantity. This value is defaulted from the MFG control file. If this field is set to NO, capacity clearance will be made for all resources.
- Availability mtrl
- The code indicates how the disposal date should be calculated.
Code Description 1 The disposal date for the component should be the first possible date where needed quantity is available. 2 All existing reservations within the lead time should be taken into consideration when calculating the disposal date for components. 3 Only Quantity on hand will be taken into consideration when calculating the disposal date. Reservations and orders will not be included.
- Enquiry type
- The code indicates the type of clearance to be made first. (Note: You can toggle between material and capacity clearance later on.)
Code Description 1 Material clearance 2 Capacity clearance