Manufacturing order maintenance, Header (PRO002B)

The purpose of this program is to maintain the header information for an existing manufacturing order.

Function keys

Alt products Maintain alternative/co-products.
PC/CC View the product costing.
Text Maintain order unique texts.
Backward reschedule Reschedule the order backwards to get a new calculated start date.
Forward reschedule Reschedule the order forwards to get a new calculated completion date.
Item
Warehouse
Status
The code indicates the status of the manufacturing order.

Valid codes are:

Variant
Drawing no
Unit
The stock or structure unit of the item. See Structure unit handling for more information.
Order type
Order number
Print vers
Item version
Order quantity
If alternative products have been defined for the item or the manufacturing order, this field displays the sum of the Item planned quant and the alternative products.

For example:
If the planned item quantity, i.e. the order quantity that was originally entered when the manufacturing order was created, is 10 and 1 alternative product is defined for the item/order, the order quantity will be 11. Note: The quantity cannot be changed if the order status is 40-60. If the order is linked to a sales order, the quantity can only be changed if the status is lower than 40 and if the new quantity is higher than the original.

Divergent +/-
The size of the difference of the original planned order quantity. This affects only the quantity on order in time axis. Note: The quantity cannot be changed if the order status is 00 – 20 or if the quantity is negative.
Planned start date

If this field is left blank click the Backward reschedule function key and the system will calculate the planned start date with help from the operation times in the operation list. You can also enter the start time of manufacturing order in the textbox beside the Planned start date textbox, when the order is planned to be started. This textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file. Note: The start time should not be greater than 24 and less than 0. Moreover, the decimal (minutes) also should not be greater than 59.

Planned compl date

If this field is left blank, click the Forward reschedule function key and the system will calculate the planned completion date using the operation times in the operation list. You can also enter the completion time of manufacturing order in the textbox beside the Planned compl date textbox, when the order is planned to be completed. This textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file. Note: The completion time should not be greater than 24 and less than 0. Moreover, the decimal (minutes) also should not be greater than 59.

New document
Indicates if new shop floor documents should be printed.
Planner
The code from Work with system user profiles indicates the signature of the planner.
Item planned quant
This field is only displayed and can only be modified if alternative items/co-products exist for the manufacturing order. The order quantity that was originally entered when the manufacturing order was created. The quantity cannot be modified if the order status is 40-60. Note: If the order is linked to a sales order, then the quantity can only be changed for the following situations:

  • If the order status is less than 40, and
  • If the new quantity is higher than the original quantity (order quantity that was entered originally when the manufacturing order was created.)

Note: The planned quantity for alternative products is displayed on the Manufacturing order maintenance, Alternative products panel.

Item reception quant
This field is only displayed if alternative items/co-products exist for the manufacturing order. This is the received item quantity, i.e. reception referring to the order quantity that was originally entered when the manufacturing order was created. Note: The total produced quantity, i.e. including both normal and alternative items, is displayed in the Produced quantity field. Received quantity of alternative products is displayed on the Manufacturing order maintenance, Alternative products panel.
Sales order
This field is only displayed if the manufacturing order is linked to a sales order. The sales order number and line to which the manufacturing order is connected.
Promised date
This field is only displayed if the manufacturing order is linked to a sales order. Displays the date when the order line was promised to be dispatched.
Project
This field is only displayed if the manufacturing order is linked to a project order. The project order number, phase and line to which the manufacturing order is connected.
Actual start date
The date and time when the manufacturing order was started. This is created by the system. It is set when the first operation is reported or when the first material issue takes place. Note: The start time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
Actual compl date
The date and time when the manufacturing order was completed. This is created by the system and is set when the manufacturing order is reported and completed. Note: The completion time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
Produced quantity
The total produced quantity, including reported approved quantity, NCC quantity and alternative items/co-products.
Scrapped
The total scrapped quantity that is reported.
NCC quantity
The total quantity that is reported as quality controlled.
Batch number
This field is only displayed if a batch number exists for the items on the manufacturing order. The batch number to which the batch controlled items belong. See Batch number for more information.
Order quantity unit
The order quantity in structure unit. This field is only displayed if the structure is defined in unit other than stock unit.
Structure unit
Produced quant unit
The receipt quantity of the manufacturing order in structure unit. This field is only displayed if the structure is defined in unit other than stock unit.
Scrapped unit
The scrapped quantity of the manufacturing order in structure unit. This field is only displayed if the structure is defined in unit other than stock unit.
NCC quantity unit
The quantity reported on quality control in structure unit. This field is only displayed if the structure is defined in unit other than stock unit.
Force QC at rec
This field is only displayed if the (MQC-REC) Manufacturing quality control at reception function is activated. Indicates if quality control reporting should be mandatory for this manufacturing order. If the QC always field is set to YES in the item structure, this field will be defaulted with YES. Note: The value entered in this field overrides the quality control definition on item structure level. This means that a quality control might take place for this order even though a specific interval is specified in the item structure.
Item pl quant unit
The item planned quantity of the manufacturing order in structure unit. This field is only displayed if the structure is defined in unit other than stock unit and alternative products exist for the manufacturing order.
Item rec quant unit
The reception quantity of the manufacturing order in structure unit. This field is only displayed if the structure is defined in unit other than stock unit and alternative products exist for the manufacturing order.