This panel displays details about a selected material for a manufacturing order history record.
- Item
- Warehouse
- Variant
- Item version
- Order number
- Order type
- Order qty
- Reported qty
- The total reported quantity.
- Pln start
- This field also displays the time when the order is planned to be started. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Act start
- This field also displays the actual start time of the order. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Dly days
- The number of days delayed between the actual start date and the planned start date.
- Pln compl
- This field also displays the time when the order is planned to be completed. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Act compl
- This field also displays the actual completion time of the order. Note: The time textbox is only displayed if the function MPL-TIME(Plan operation by date/time) is activated in the Function control file.
- Dly days
- The number of days delayed between the actual completion date and the planned completion date.
- Sequence
- Component
- The code that identifies the component.
- Description
- The description of the component.
- Pc quantity
- The planned required quantity.
- Cc quantity
- The real issued quantity.
- Pc qty unit
- The planned required quantity in structure unit for the component. This field is only displayed when Structure unit has been used. See Structure unit handling for more information.
- Cc qty unit
- The real issued quantity in structure unit for the component. This field is only displayed when Structure unit has been used. See Structure unit handling for more information.
- Mtrl unit
- The structure unit for the component item. This field is only displayed when Structure unit has been used. See Structure unit handling for more information.
- Pc amount
- The product cost value of the component.
- Cc amount
- The real cost value of the component.
- Diff quant
- The difference between the pc and cc quantity.
- Diff amount
- The difference between the pc and cc amount.