Product costing online, Bill of material (BAS050F)

The purpose of this program is to display values that are related to the product costing calculation concerning quantities and costs. On this panel you can also maintain values. A base structure can be used and then modified according to existing components and the added new components.

Note: If a structure has been modified you can only save it as a simulation product costing.

Item
Calc date
The date used for when the right prices and overhead were retrieved.
Cost model
The cost model id used for product costing.
It cost type
The item cost type indicates from where the component prices have been retrieved during the product costing calculation.

Valid codes are:

Code Description
1 Average cost
2 Standard cost
3 FIFO
4 Simulation cost
Std quant PC
The quantity in stock unit that the product costing is based on.
Struct quant
Variant
Warehouse
Struct unit
Seq no
Component
The item that is included as a component in the bill of material.
Variant
Comp unit
Displays/Enter the unit for the component, that is, either component unit or stock unit. Note: You can enter the unit in this field only in Add mode. In Change and Display mode, this field is read-only.
Quantity
The quantity in stock unit, in up to 3 decimals, of components included in the bill of material. The quantity field can be both positive and negative, if negative; the material is handled as a by-product in the system.
Std quant PC
The quantity in stock unit that the product costing should be based on. Note: This quantity is only valid to set for items with item type 1 or 2.
Set-up quantity
Optional entry. Enter the fixed set-up quantity for materials. This set-up quantity can be deemed as an estimated reservation that you plan on consuming for the machine set-up before real production, and is independent of the order’s quantity. When manufacturing orders are entered, the components required quantity is calculated as follows: order quantity x component quantity + fixed set-up quantity.

Example:
Fixed set-up quantity = 10
Order quantity = 5
Component quantity = 1
Component required quantity = 15

Waste pct
The percentage indicates how many extra items must be produced due to production waste. The value is used to re-calculate the structure amounts during the reservation and picking for the manufacturing order.
Cost price
The cost price to be used to calculate product costing to parent item. Note: This cost price is only valid to set for items with item type 3 or 4.
Cost unit
The unit used to define the cost price.
Amount TL
The amount this level for sub-assembly item. The amount is presented in system currency for one parent item unit.
Amount LL
The amount lower levels for sub-assembly item. The amount is presented in system currency for one parent item unit.
Total amount